Monroe Grain Bin Construction

February, 2022

February 14th

Ground preparation on the new grain bin has begun.

February, 2022

February 15th

Ground heating to remove frost.

February, 2022

February 22nd

First layer of dirt stripped and ground being heated to remove more frost.

February, 2022

February 24th

More heating to remove frost.

March, 2022

March 1st

Forming for concrete.

March, 2022

March 4th

Pouring concrete.

March, 2022

March 14th

Getting ready for more concrete.  

April, 2022

April 1st

Pouring the grain bin floor. 

April, 2022

April 8th

More deliveries and finishing up the concrete.

April, 2022

April 11th

The concrete work is complete and the first bin section is being assembled.

Staging area including the roof supports.  

April, 2022

April 12th

The first support section of the roof is in place.

April, 2022

April 19th

Check out the changes in the Monroe skyline!  In less than one week, the bin is up, and they will finish putting on the stiffeners and tie it down today.

May, 2022

May 11th

The tower and catwalk are nearing completion. The crane should arrive in the next few days to swing it all into place.

August, 2022

August 9th

The conveyors have arrived and will now be installed.