Ground preparation on the new grain bin has begun.
February, 2022
February 15th
Ground heating to remove frost.
February, 2022
February 22nd
First layer of dirt stripped and ground being heated to remove more frost.
February, 2022
February 24th
More heating to remove frost.
March, 2022
March 1st
Forming for concrete.
March, 2022
March 4th
Pouring concrete.
March, 2022
March 14th
Getting ready for more concrete.
April, 2022
April 1st
Pouring the grain bin floor.
April, 2022
April 8th
More deliveries and finishing up the concrete.
April, 2022
April 11th
The concrete work is complete and the first bin section is being assembled.
Staging area including the roof supports.
April, 2022
April 12th
The first support section of the roof is in place.
April, 2022
April 19th
Check out the changes in the Monroe skyline! In less than one week, the bin is up, and they will finish putting on the stiffeners and tie it down today.
May, 2022
May 11th
The tower and catwalk are nearing completion. The crane should arrive in the next few days to swing it all into place.
August, 2022
August 9th
The conveyors have arrived and will now be installed.